- JPMorgan Chase and Starwood Property Trust provided a $2 billion loan for a 100-acre AI-focused data center in Utah, highlighting the growing scale of data center investments.
- The facility, developed by CIM Group and Novva Data Centers, will deliver 175 megawatts of power and is already fully leased, reflecting strong demand for AI infrastructure.
- Data center construction is shifting to regions with abundant power, water, and supportive local governments, as traditional hubs face land and power constraints.
- Water scarcity and power availability remain key challenges for data center development in the Western U.S.
What Happened?
Developers CIM Group and Novva Data Centers secured a $2 billion construction loan from JPMorgan Chase and Starwood Property Trust to build a 100-acre data center campus in West Jordan, Utah. This marks one of the largest loans for a data center project, reflecting the growing demand for facilities to support artificial intelligence. The campus, capable of providing 175 megawatts of continuous power, is already fully leased, with completion expected by 2026. Utah’s low risk of natural disasters and innovative water-efficient cooling systems make it an attractive location, though water scarcity and power availability remain challenges.
Why It Matters?
The loan underscores the rapid growth of the data center market, driven by the increasing power and infrastructure needs of AI technologies. For investors, this signals a shift toward larger, more capital-intensive projects with pre-leased commitments, reducing speculative risks. The move to regions like Utah highlights the need for alternative locations as traditional hubs face limitations in power, land, and public support. However, challenges such as water scarcity and extended timelines for securing power could slow future developments, impacting the pace of AI infrastructure expansion.
What’s Next?
The Utah data center is part of a broader trend of hyperscalers like Amazon, Microsoft, and Meta expanding into new regions with favorable conditions for large-scale projects. Investors should monitor how developers address water and power constraints, as these factors could influence the feasibility of future projects. Additionally, the continued rise in AI-driven demand is likely to push data center investments to record levels, with opportunities in emerging markets and innovative cooling technologies becoming key areas of focus.